Off-Plan to Move-In: A Furnishing Timeline for New-Build Owners
Furniture Packages
November 23, 2026

Off-Plan to Move-In: A Furnishing Timeline for New-Build Owners

My stage-by-stage furnishing timeline for off-plan buyers on the Costa del Sol: when to plan, measure, order and deliver, from reservation to move-in.

Buying off-plan gives you something most buyers never get: time. Used well, that time means you can collect your keys, deal with the snagging list and sleep in a finished home soon after the repairs are done. This is the furnishing timeline I give new-build owners, from the reservation to the first night in the apartment.

When should you start furnishing an off-plan new build in Spain?

Start the design work about six months before your expected keys date, and confirm your proposal about three months before. Measure again once the apartment is built, deliver after the snagging repairs, and keep the installation date flexible until the developer confirms handover. A two-bedroom package from me starts at €16,500 + IVA.

That is my planning advice, not a rule from any developer or supplier, and every building runs to its own calendar. The owners who move in smoothly are rarely the ones who ordered earliest. They are the ones who did the right thing at each stage: nothing rushed while the building was a crane and a sales office, then a clear sequence once a completion date was real.

Below is the sequence I recommend, stage by stage. I have written it for the typical off-plan apartment or townhouse on this coast, handed over with a fitted kitchen, finished bathrooms, built-in wardrobes and empty rooms everywhere else.

Newly completed open-plan living room in a Costa del Sol new-build apartment, furnished with a linen sofa, oak coffee table and dining table, with sliding glass doors to a terrace and sea view

The off-plan timeline at a glance

Before the detail, here is the whole picture. The months are counted back from the date you expect to collect your keys, because that is the only date that really matters for furniture.

Infographic timeline for furnishing an off-plan new build on the Costa del Sol, from reservation and construction to six and three months before keys, keys and snagging, installation, move-in and the first year

  1. Reservation and contract. Collect the documents. Buy nothing.
  2. During construction. Decide how you will use the home, set a budget, and think about style.
  3. About six months before keys. Book a design call, choose a style and package, and plan the lighting.
  4. About three months before keys. Confirm the proposal and pencil in an installation window.
  5. Keys and snagging. Inspect, report defects, and measure the finished rooms.
  6. After snagging repairs. Delivery, assembly, installation and styling.
  7. Move-in. Arrive to a finished home.
  8. The first year. Note anything that appears and report it to the developer.

Stage 1: Reservation and private contract

An off-plan purchase in Spain usually follows the same broad shape: a reservation, a private purchase contract with payments on account during construction, and completion at the notary when the building is finished. Your lawyer will explain your own contract. What I can tell you is which documents to keep for the furniture stage.

Two legal points are worth understanding at this stage, because they shape how much confidence you can place in the dates. Under Spain's building law, Ley 38/1999 de Ordenación de la Edificación, a developer who takes money from buyers before the home is finished must guarantee its return, plus legal interest, through an insurance policy or a bank guarantee, from the moment it holds the building license. The money must also be paid into a special account kept separate from the developer's other funds. Spain's consumer ministry explains that the developer must give you the document proving that guarantee when you sign the contract.

The Junta de Andalucía's consumer guidance also reminds buyers that the price is paid in full and the keys are handed over when the public deed is signed at the notary. In other words, the day you sign the escritura is normally the day you get the keys, and that is the date your furniture plan works back from.

For furniture, the useful documents from this stage are:

  • The floor plans with room dimensions, ideally the architect's plans rather than the brochure version.
  • The memoria de calidades, the specification list for floors, doors, wardrobes, kitchen, bathrooms and air conditioning.
  • The electrical plan, if the developer will share it, showing ceiling points, sockets, TV points and terrace lights.
  • The delivery date in your contract. Note it, but do not plan furniture around it yet.

At this stage I would not buy a single piece of furniture. A sofa ordered two years ahead has nowhere to live.

Stage 2: During construction

Construction is the long middle of an off-plan purchase, and the easiest stage to waste. This is the time to make the decisions that do not depend on exact measurements.

Decide how the home will be used

A home you live in all year, a second home you visit for a few months, and a holiday rental are three different briefs. A rental needs fabrics that clean easily, enough seating and dining for the number of guests, and a layout that photographs well. If letting is part of the plan, read about what Andalusia's holiday rental rules require inside the apartment now, while there is still time to plan for it.

Set a realistic budget

Off-plan buyers often budget carefully for the purchase price, taxes and fees, and then treat furniture as something to sort out later. I would rather you put a real number on it now. My package prices are published, so you can plan with the figures:

  • Essentials: from €16,500 + IVA for two bedrooms, from €19,990 + IVA for three bedrooms, €2,995 + IVA for each extra bedroom.
  • Elevated: from €25,500 + IVA for two bedrooms, from €29,990 + IVA for three bedrooms, €3,995 + IVA for each extra bedroom.

Prices are shown before IVA, which is added at the current rate on your invoice. For a fuller picture, including the costs owners forget, see my guide to what it costs to furnish an apartment on the Costa del Sol.

Start thinking about style

I design complete furniture packages in three styles. Mediterranean Calm is light oak, soft linen, warm whites and sand tones. Contemporary Warmth brings darker woods, clean lines and rich textures, and it is the style I often suggest for newer developments. Coastal Elegance is crisp whites and soft stone, with blue in the textiles, lamps and ceramics. You do not need to choose yet. Notice which one you keep coming back to.

Ask about the electrics while changes are still possible

Some developers accept small changes while the building is going up, such as an extra socket or a light point, and many do not. If yours does, ask early. The change I would ask for most often is a light point on each side of the bed, because pendant lights above the nightstands clear the bedside table and look far better than a lamp squeezed next to a phone charger. Electrical work such as new light points is carried out by your electrician, and I prepare the layout so they know exactly what to do.

Stage 3: About six months before keys

When the developer gives you a completion window you can believe, usually once the structure is closed and the interiors are under way, it is time to start the design work properly. For most owners, I suggest this happens around six months before the expected keys date.

Here is what happens at this stage:

  1. A first call. You share the floor plan, a few photos or renders and your expected move-in date. I ask how you will use the home and what matters most to you.
  2. Style and package. I recommend the style and package that fit your home and the way you will live in it, Essentials or Elevated.
  3. Layout planning on the plans. I plan every room from the developer's drawings: the sofa against the TV point, the dining table, the beds against the wardrobe doors.
  4. Lighting. I plan the lamps around the ceiling points shown on the electrical plan, and flag anywhere an extra light point would make a real difference.
  5. The terrace. Outdoor furniture is included in every package, and I design the terrace setup from the plan dimensions.

None of this needs you in Spain. The whole process happens by video call, email and WhatsApp.

Light-filled bedroom in a newly built Costa del Sol apartment with a linen upholstered bed, oak bedside tables, pendant lights above the nightstands and floor-to-ceiling sliding windows

Why I plan from drawings but confirm in the room

Drawings are excellent for layout and poor for surprises. A column that sits further into the room than the plan suggests, or a terrace that loses depth to a planter, can change which sofa fits. So I treat the key dimensions as provisional until the apartment is built.

Stage 4: About three months before keys

By now the developer should be talking about a finish date in weeks rather than seasons. This is the point where I suggest you confirm your proposal.

My proposal shows every piece, room by room, with a fixed price before anything is ordered. Some choices, such as a different fabric, a sofa upgrade or added pieces, may change the price, but you see every change in the proposal before you confirm. You can also swap any piece for one from another style at the same package level at no extra cost. Once you approve the proposal and pay the deposit, your installation date is secured, and from there I coordinate the orders, suppliers and deliveries, with updates by WhatsApp. You can see the six steps on how my furniture packages work.

Why three months and not three weeks? Because the pieces I specify are solid, well-made furniture from trusted European makers, not flat-pack and not showroom leftovers, and many come in the fabric color, size and finish you choose. Pieces like that take time to make and transport, and the actual dates for your order are confirmed when we plan it. Confirming early means the furniture is ready when the rooms are.

Hold the installation window loosely

Off-plan completion dates can move, and the date in a sales conversation is not always the date in your contract. I pencil in an installation window based on the expected handover, then confirm it once the handover date and the snagging repairs are firm. I would rather move a window by a few weeks than send a delivery team to a building with no working lift.

Stage 5: Keys, completion and snagging

Completion day is when you sign the deed at the notary, pay the balance and receive the keys. For furniture, it is the start of the most important week.

The occupation paperwork and the utilities

In Andalusia, the occupation of a newly built home is now generally authorized by a declaración responsable de ocupación filed with the town hall, accompanied by the final certificate of works. That is set out in article 138 of Andalusia's land law, Ley 7/2021 (known as LISTA). You will still hear many people call it the licencia de primera ocupación, the first occupation license, which is the older name.

That document matters for move-in because the same law, in article 142, says that electricity, water, gas and telecom companies must ask for the occupation license or declaration before they sign the definitive supply contracts. Your lawyer or the developer can tell you when the paperwork is in place and the utilities can be put in your name. I plan installation for a date when the apartment has power and water, because the team needs to test lamps, and nobody wants to style a home by the light of a phone.

Snagging

Snagging means inspecting the finished apartment and listing every defect for the developer to fix: a chipped tile, a door that does not close properly, a scratch on the glass, paint that misses a corner. You can do it yourself or hire an independent inspector, and the developer then works through the list.

I deliver after the snagging repairs are complete. Painters and tilers work faster and more carefully in empty rooms, and a new sofa is the last thing you want next to someone sanding a door frame. I explain this in my guide to furnishing a new apartment in Estepona.

Measuring the finished rooms

The week you collect your keys is also when the key measurements get confirmed. I check the ones that decide whether the plan works on delivery day:

  • The lift, inside dimensions and door width, because it decides whether a three-seat sofa goes up whole.
  • Every door on the route, from the building entrance to each bedroom.
  • The terrace depth, measured from the glass to the balustrade, which decides the dining table.
  • The windows, if you want curtains. Curtains and window treatments are a custom add-on, because every window is a different size, so I measure and quote them for your home.
  • The ceiling points and sockets as built, compared with the plan.

If you are not in Spain, your agent, your property manager or a key holder can let us in. I coordinate with them directly.

Terrace of a new-build apartment on the Costa del Sol furnished with a teak dining table, woven outdoor chairs and a low sofa with sand-colored cushions, overlooking a pool and the sea

Stage 6: Delivery and installation after the repairs

Once the repairs are signed off and the installation date is confirmed, delivery, assembly, installation and final styling are all included in the package. There are no separate transport fees, no handyman bills and no styling charges.

On a typical new-build installation, I think about the building as much as the apartment:

  • The community. The new community of owners may have rules on delivery times, lift protection or where a van can park. I check before the day.
  • Other owners moving in. In a new building, several apartments can be furnished in the same weeks. Booking the lift early saves a lot of waiting.
  • The order of rooms. Beds and wardrobes first, then the living room, then the terrace, then lighting and styling last.

Final styling is what makes a room feel finished rather than delivered: the rug squared to the sofa, the lamps on, the ceramics placed, the bed made. A live plant chosen for your light and welcome gifts picked for how you will live in the home are waiting when you arrive.

Stage 7: Move-in

If you are in Spain, you walk into a finished home. If you are abroad, you receive photos and a video walkthrough first, and many owners see the finished home for the first time when they arrive with their suitcases.

My only advice for move-in week is to live in the home for a few days before you add anything. You will notice which corner wants a reading chair and which wall is better left empty.

Stage 8: The first year

The first year in a new build is when small things show themselves: a hairline crack in a wall, a door that starts to stick, a tile that sounds hollow. Spain's building law sets out periods of responsibility for material damage. The builder answers for defects in finishes for one year, and those involved in the construction answer for defects affecting habitability for three years and for structural defects for ten years. These periods count from the formal reception of the works between the developer and the builder, not from the day you collect your keys, so do not wait to report something.

Keep a simple note on your phone of anything that appears, with a photo and a date, and send it to the developer.

Mistakes I see on off-plan furnishing

These are the patterns that make move-in harder than it needs to be:

  • Ordering against the brochure date. A sales date is a hope. A completion date is a plan.
  • Buying for the show apartment. A show apartment is dressed to sell, and its pieces are chosen for photographs. Use it for mood, not measurements.
  • Leaving lighting to the end. By the time the furniture arrives, it is too late to move a light point without an electrician and some dust.
  • Scheduling delivery on completion day. Keys, utilities and snagging all happen that week. Furniture should come after them.
  • Buying piece by piece from abroad. Five suppliers means five deliveries, and someone has to be there every time.

Where my packages fit in an off-plan purchase

I work along the Costa del Sol, mostly from Benalmádena to Manilva, including Benahavís and the surrounding areas. A package suits an off-plan buyer because it matches the way a new build is handed over: everything apart from the kitchen and bathrooms is empty, and you need the whole home finished at once rather than room by room. You get one English-speaking contact from the first call to the final placement, one fixed proposal, and one installation.

If you want to see exactly what that includes room by room, I wrote a detailed guide to what is included in a furniture package. For answers to the shorter questions, such as IVA and customization, my furniture package FAQ covers them.

If you are not ready for a full project and would like a professional opinion on the apartment first, I also offer a 2-hour in-home consultation for €279. It is useful once you have keys and want a clear plan before you spend anything. For renovation work beyond furniture, see my interior design and renovation services.

Frequently asked questions

When should curtains be measured in a new-build apartment?

Measure curtains once the apartment is built and the windows, ceilings and any recesses are final, normally in the week you collect the keys. Plans and renders are not accurate enough for curtains. I measure and quote curtains as a custom add-on, because every window is a different size.

Do the utilities need to be connected before the furniture arrives?

Yes, I recommend it. In Andalusia, utility companies need the occupation license or declaration before signing the definitive supply contracts, so power may not be in your name on completion day. I plan installation for a date when the apartment has electricity and water, because lamps are tested and the home is styled on the day.

Should I plan the furniture around the show apartment?

Use the show apartment for mood and proportions, but not for measurements or shopping lists. It is dressed to sell and photograph, and your own apartment may face a different way, sit on another floor or have a different terrace. I plan from your floor plan and confirm the key dimensions once your unit is built.

What if the developer changes the completion date?

It happens, which is why I hold the installation window loosely. Your proposal and design work can go ahead, and I confirm the installation date once the handover date and the snagging repairs are firm. If the date moves, tell me as soon as you hear, and I will adjust the plan with you.

Planning around a completion date

If you have bought off-plan, or you are about to, send me the floor plan, a few photos or renders and the date the developer expects to hand over the keys. I will tell you which package fits, which style suits the light and the view, and how I would time the design, the order and the installation around your completion.